Conceptual cost estimates
The following activities are foreseen to complete the construction of the outfall pilot
Project Management
-
ABB-BP or LGU representative full time
-
Stakeholder management
-
Expert support (Nature based solutions)
-
Expert support (Coastal engineering)
-
Contracting
-
Supervision
Detailed Design
-
Basis of Design
-
Wave impact assessment based on empirical calculations
-
Embankment design
-
Planting scheme
Surveys
-
Bathymetric
-
Material testing dike
Construction
-
Demolish Revetment
-
Supply core material and clay
-
Supply coronets
-
Planting
Conceptual cost estimates green embankments (2,000 m)
Project Management | $ 34,000 |
Revetment removal | $ 77,000 |
Green embankment construction | $ 603,000 |
Contingency (10%) | $60,300 |
Total costs (conceptual) | $ 663,300 |